Construction at Blair Executive Airport

Aug 11
1 min read

Just a reminder that scheduled construction at Blair Executive Airport begins next week.


Starting Monday, August 17, the runway, parallel taxiway, and turf area will be closed Monday through Friday from 7 AM to 7 PM while crews complete important improvements. The project is expected to take up to 50 working days, but construction could be completed sooner if weather and progress allow.


If you utilize Blair Executive Airport, please plan accordingly and always respect posted closures and construction zones to help keep everyone safe